Supporting the launch of one of Poland's largest power plants with demineralized water
Our client is a global leader in engineering specializing in thermal power and environmental technologies. They provide comprehensive services, including development, design, manufacturing, construction, and commissioning of turnkey fossil-fired power plants.
Secure flawless plant commissioning with Mobile Water Solutions
offering
presence
solution
The Challenge
Our client played a pivotal role in the construction and commissioning of one of Poland’s largest power plants—a high-efficiency 500MW brown coal-fired unit. Leveraging their longstanding relationship with Mobile Water Solutions, the client approached our team to support the power plant’s start-up (Phase 1) by providing 100m³/h of demineralized water.
The Solution
Mobile Water Solutions responded by supplying four mobile filtration units MOFI RW300F, one mobile filtration unit MOFI 3×60, one mobile reverse osmosis unit MORO 4×25 T, one mobile deionization unit MODI 15000 T, and one mobile pump MOPS 170i. The mobilization commenced with a three-week production period, followed by three weeks of standby, and concluded with an additional five days of demineralized water production.
Benefits
Our competitive technology offering, coupled with our local presence, facilitated swift response, asset delivery, and seamless communication with the on-site team, ensuring the successful launch of one of Poland’s largest power plants.